Re: [商管] [作業研究] 100年清大 等候線理論

看板Grad-ProbAsk作者 (皮卡丘)時間14年前 (2012/02/07 21:37), 編輯推噓0(000)
留言0則, 0人參與, 最新討論串2/2 (看更多)
※ 引述《carthage (攝影是一種生活)》之銘言: : 今天寫清大考古題的時候,有一題的答案感覺很怪,想請有考作業研究的版友們解惑XD : 100年清大,作業研究,第六題,題目如下 : Machinists who work at a tool-and-die plant must check out tool from a tool : center. An average of ten machinists per hour arrive seeking parts. At present, : the tool center is staffed by a clerk who takes an average of 5 minutes to : handle each request for tools. Since machinists are paid $10 per hour, each : hour that a machinist spends at the tool center costs the company $10. The : company is deciding whether or not it is worthwhile to hire (at $4 per hour) : a helper for the clerk. If the helper is hired, the clerk will take an average : of only 4 minutes to precess requests for tools. Assume that service and : inter-arrival times are exponential. Based on the cost analysis, should the : helper be hired? : 這是一題M/M/1的等候線考題 : 補習班給的答案上面寫著 : 原方案: : 每個工人的時薪Cr是10元,顧客的等候成本Cw也是10元 : λ=10(位/小時) μ= 12(位/小時) : 總成本= 1*10+10*(10/20-10)=60元/小時 : 只是我在題目敘述一直找不到「顧客的等候成本Cw也是10元」這項資訊, : 是我英文太爛了嗎?還是答案寫錯?還是我解題方向錯了? : 以上問題,拜託大家了!我想了一個晚上....囧 : 感激不盡 : 只是我在題目敘述當中一直找不到 你的總成本值應該有點寫錯喔 總成本=1*10+10*(10/12-10)=60才對 基本上你的想法沒有錯 只是最後一個地方可能沒有很了解吧 每個顧客在系統中只要等待一個小時就要10$的成本 而你的L=10/(12-10)=5就是在系統中期望的人數 每當系統多了一個人就會多一個等待所造成的成本 今天總共有五個人 因此每小時的等待成本就要算五個人的份量 所以Cr+Cw*L就會是總成本了 -- ※ 發信站: 批踢踢實業坊(ptt.cc) ◆ From: 140.113.123.225
文章代碼(AID): #1FCIa3e9 (Grad-ProbAsk)
文章代碼(AID): #1FCIa3e9 (Grad-ProbAsk)